$34bn and counting – beware cost overruns in an era of megaprojects

  • Written by Greg Moran, Senior Associate, Grattan Institute

A Grattan Institute report[1] released today finds Australian governments spent A$34 billion, or 21%, more on transport projects completed since 2001 than they first told taxpayers they would. And as we enter the era of megaprojects in Australia, costs continue to blow out.

Transport projects worth A$5 billion or more in today’s money were almost unheard of ten years ago. Today, as the chart below shows, megaprojects make up the bulk of the work under way across the country.

$34bn and counting – beware cost overruns in an era of megaprojects Author provided These megaprojects include WestConnex[2] in Sydney, West Gate Tunnel[3] in Melbourne and Cross River Rail[4] in Brisbane. And this is to say nothing of some enormous projects being planned, such as Melbourne’s Suburban Rail Loop[5]. We are also hearing calls to add to this bulging pipeline. In June, the transport and infrastructure ministers of all states and territories said[6] they were “clearing the way for an infrastructure-led recovery” from the COVID-19 recession. Read more: We may live to regret open-slather construction stimulus[7] Cost overrun risks rise with project size The Grattan report, The rise of megaprojects: counting the costs[8], sounds a warning about the risks of this approach. The report uses the Deloitte Access Economics Investment Monitor[9] to look at the final cost of all public road and rail projects worth A$20 million or more and completed since 2001. As the chart below shows, we found bigger projects overran their initial cost estimates more often and by more. $34bn and counting – beware cost overruns in an era of megaprojects Author provided Almost half of the projects with an initial price tag of more than A$1 billion in today’s money had a cost overrun. These projects overran their initial costs by 30% on average. The extra amount spent on some megaprojects was the size of a megaproject itself. Cost announcements before governments were prepared to commit formally to a project were particularly risky. Only one-third of projects had costs announced prematurely, but these accounted for more than three-quarters of the A$34 billion overrun. Read more: Missing evidence base for big calls on infrastructure costs us all[10] When early costings of infrastructure turn out to be too low, it distorts investment planning in three ways: underestimating the costs of transport infrastructure can lead to over-investing in it relative to other spending priorities if governments misunderstand the uncertainty in a project’s cost at the time they commit to it, their decision to invest in that project was made on an incorrect basis because unrealistic cost estimates are more prevalent for larger projects, governments are more likely to over-invest in larger projects. There’s also a fourth and no less important problem: when unrealistically low cost estimates are announced, the public is misled. Despite the experience of the past 20 years, the costs of big projects continue to be underestimated. The chart below shows A$24 billion more than first expected will be spent on just six mega megaprojects (that is, projects with an initial cost estimate of A$5 billion or more) now under construction. Overruns on other megaprojects have been reported[11] too. $34bn and counting – beware cost overruns in an era of megaprojects Author provided Read more: Transport promises for election 2019: the good, the bad and the downright ugly[12] What needs to be done? With megaproject costs continuing to blow out, governments should take immediate steps to manage better the portfolio of work under way — particularly if they are looking to add to it in the name of economic stimulus. Each state’s auditor-general should conduct a stocktake of current projects. This would give the public and the government a clear picture of the situation. Minister speaking in parliament Ministers should report to parliament any changes in project costs, dates and benefits as they become known. James Ross/AAP Ministers should begin reporting to parliament on a continuous disclosure basis. Any material changes in expected costs, benefits or completion dates of very large projects should be disclosed. Steps should be taken to put decisions on the incoming batch of projects on a sounder basis, too. When announcing a cost, ministers and government agencies should disclose how advanced the estimate is. If the proposal is at an early stage, they should quote a range of estimates. Governments should also require their infrastructure advisory bodies to at least assess — if not approve — large proposals before funding is committed. Looking further ahead, action is needed to stop the pattern of spending billions more than expected on megaprojects. State departments of transport and infrastructure should devote more resources to identifying modest-sized transport infrastructure proposals. Read more: The PM wants to fast-track mega-projects for pandemic recovery. Here's why that’s a bad idea[13] And governments need to start learning from the past. Detailed project data, particularly on expected and actual costs, should be centrally collated in each state. Post-completion reviews should be mandatory on all large projects. These reviews should be published. If there is no change in the way infrastructure is conceived and delivered in Australia, then the era of the megaproject will indeed mean megaproblems.

References

  1. ^ Grattan Institute report (grattan.edu.au)
  2. ^ WestConnex (www.westconnex.com.au)
  3. ^ West Gate Tunnel (westgatetunnelproject.vic.gov.au)
  4. ^ Cross River Rail (crossriverrail.qld.gov.au)
  5. ^ Suburban Rail Loop (suburbanrailloop.vic.gov.au)
  6. ^ said (www.transportinfrastructurecouncil.gov.au)
  7. ^ We may live to regret open-slather construction stimulus (theconversation.com)
  8. ^ The rise of megaprojects: counting the costs (grattan.edu.au)
  9. ^ Deloitte Access Economics Investment Monitor (www2.deloitte.com)
  10. ^ Missing evidence base for big calls on infrastructure costs us all (theconversation.com)
  11. ^ reported (www.theage.com.au)
  12. ^ Transport promises for election 2019: the good, the bad and the downright ugly (theconversation.com)
  13. ^ The PM wants to fast-track mega-projects for pandemic recovery. Here's why that’s a bad idea (theconversation.com)

Authors: Greg Moran, Senior Associate, Grattan Institute

Read more https://theconversation.com/34bn-and-counting-beware-cost-overruns-in-an-era-of-megaprojects-149149

Business Times

Insolvencies have spiked – would a law change let more businesses…

New Zealand has been experiencing a striking rise in company failures, focusing attention on the role of directors when...

How Businesses Are Generating Profits in a High-Inflation Economi…

Inflation in Australia and globally has surged to multi-decade highs since 2021, driven by pandemic supply shocks, energy...

The Effects of the War in the Middle East on Australian Small Bus…

The war in the Middle East is not a distant geopolitical event for Australia. In an interconnected global economy, confli...

The Times Features

To Make Your Home & Garden Stand Out In Moorabbin – Try These Excellent Ideas.

We shouldn’t always be ‘trying to keep up with the Joneses’, but it is a common human trait to wan...

Travel Trends: Where Are Australians Going in 2026?

For Australians, travel has always been more than just a holiday. It is a cultural habit, a reward...

Applications Open for TasPorts Industry Support Program

TasPorts has opened applications for its 2026 Industry Support Program, offering $100,000 in f...

STATEMENT FROM DEPUTY LEADER OF THE NATIONALS DARREN CHESTER

I'm incredibly honoured to have been elected Deputy Leader of The Nationals Federal Parliamentary ...

Grill'd Oscar Piastri's burger just landed at Coles

Grill’d is putting the pedal down with the launch of an all-new Oscar Piastri Burger on 10 Febru...

Tasmanian MP Andrew Wilkie has issued a statement regard Robodebt

 A STATEMENT ON NACC ROBODEBT FINDINGS - Andrew Wilkie The National Anti-Corruption Commission h...

Can exercise reduce period pain? And what kind is best?

Having your period can be a painful experience. Period pain, also known as dysmenorrhea, is a...

Tasmania in 2026: Opportunity, Pressure and the Island State’s Defining Moment

Tasmania has long held a unique place in the Australian story. It is a state known for natural b...

Middle East war set to push inflation higher than forecast, warns RBA deputy governor

The Reserve Bank’s Deputy Governor Andrew Hauser says inflation in Australia looks likely to be ...