A clean energy grid means 10,000km of new transmission lines. They can only be built with community backing

  • Written by Asma Aziz, Lecturer in Power Engineering, Edith Cowan University
A clean energy grid means 10,000km of new transmission lines. They can only be built with community backing

If you drive through central Victoria, you might wonder at the signs reading “Piss off AusNet” in shop windows or even mown into grassland. Communities and farmers are pushing back[1] against plans for new 85-metre towers and transmission lines needed to transmit renewable power to the cities.

Expect to see many more of these stories in coming years. To decarbonise by 2050, we must build more than 10,000 kilometres of new high-voltage transmission lines to carry renewable energy. That’s according to the Australian Energy Market Operator’s new plan[2] for the energy system, which Labor committed to[3] before the election.

But local opposition could derail this – even though the influential National Farmers Federation has backed the plan[4]. The plan recognises this: “As the rate and scale of transformation continue to accelerate … social licence will require urgent and continuing focus.”

Read more: We calculated emissions due to electricity loss on the power grid – globally, it's a lot[5]

Why do we need more transmission lines?

High-voltage transmission lines can deliver electricity economically and efficiently over longer distances. For decades, we’ve used these transmission lines to balance electricity demand and generation.

Australia’s National Electricity Market is one of the world’s longest interconnected power systems, able to move power between the east coast states, Tasmania and South Australia.

To ramp up our renewable electricity base, governments have introduced renewable energy zones – our sunniest and windiest places – to encourage investment. But these zones are often far from energy-hungry cities. That’s where transmission lines come in.

Building more high-voltage lines will let us make the future grid more resilient, enabling electricity to be brought in from other areas if one zone isn’t generating as much, or exporting it if there’s a spike in production. This is a key way of tackling the intermittency issue with renewables. If the sun isn’t shining or the wind isn’t blowing in one area, we can draw energy from the places where it is.

solar farm
Solar and wind farms need grid connections - and that means new powerlines. Zbynek Burival/Unsplash, CC BY[6]

Are there any alternatives?

As battery technology and other electricity storage methods improve, it may be possible to ramp up storage methods rather than rely on large new transmission links.

Huge and sparsely populated Western Australia is leading the way on this front. To slash transmission costs, the state has rolled out more than 100 standalone power systems that combine renewables and storage. Over the next 10 years, WA plans another 4,000 of these.

This model shows us what could be possible for sections of the east coast’s grid. We could see a decentralised electricity system, in which local renewable energy is generated and stored locally in standalone power systems or micro-grids. Towns like Victoria’s Yackandandah[7] are pioneering this local-first approach.

We could defer or reduce the scale of these mammoth transmission network projects and make the most of our existing transmission lines by strategically deploying virtual transmission capacity[8]. That means putting battery storage or small-scale pumped hydro in place, cutting the need to source electricity from distant sources while maintaining supply and demand balance.

Read more: Will NIMBYs sink new clean energy projects? The evidence says no – if developers listen to local concerns[9]

There’s a lot more work to do on this front before virtual transmission can start reducing how much new transmission infrastructure we will need. Early virtual transmission projects like the Kennedy Energy Park[10] have shown us we need a better technical understanding of how they work best, as well as updated regulations[11].

Utilities like Powerlink Queensland are exploring alternatives such as duplicating existing transmission lines or planning lines for areas already under development, such as along highways or forest tracks.

Community advocates worried about the visual and physical impact of new transmission lines often argue for cables to run underground.

This is possible, but can be more expensive. To put these high-voltage lines safely underground, you need trenches 2-3 metres deep, dug in parallel, with inspection bays every 800-1,000 metres. Compared with transmission towers, this actually causes a higher direct impact on the land.

Not only that, but you cannot allow deep-rooted trees and shrubs within the easement, which means maintenance. If there’s a fault, you have to excavate the affected land. Major bushfires can also pass significant heat through the ground to the cables, so this must be taken into account.

Does that rule out underground transmission lines? Not entirely. In fact, in some cases, it could be cost-effective, as the proposed Star of the South[12] offshore wind project demonstrates.

trench digging Undergrounding power cables can be cost effective for some projects - but it’s a case by case approach. Shutterstock

Could community opposition slow the clean energy shift?

It is a risk. Efforts to get emitting sources of electricity out of our grid will face a very real bottleneck based on the social acceptance of new high-voltage transmission lines.

Even though 83% of us[13] now recognise climate change as a threat, people can change their views when clean energy solutions are proposed near them. This is nothing new – the “not in my backyard” issue is well-known.

So how can we deal with community pushback? First, we need to acknowledge that these transmission lines are an imposition. They have a significant footprint on their land corridors, in the form of tall towers, conductors, and the need for access.

Local landholders, neighbours, and the broader community often perceive[14] these types of development – regardless of the need – as a symbolic intrusion on their personal property.

Victorian farmers and residents protest the AusNet project in the belief the new infrastructure will mean loss of control over their lands, an uglier landscape, and possible restrictions on farming practices such as irrigation. Their concerns are legitimate. But the need is also great, and time is limited.

We know what doesn’t work in these settings. The traditional approach for big infrastructure items has been dubbed decide, announce and defend. This would be a mistake.

Instead, utilities and planners should focus on open community discussions over the environmental impact of the proposed above-ground transmission lines compared to the costs and impacts of underground cabling, as well as virtual site visits. By laying out the issue clearly for the public to see, utilities have a better chance of gaining the social licence – community permission – to actually build the infrastructure we will need.

Read more: A 21st-century reinvention of the electric grid is crucial for solving the climate change crisis[15]

References

  1. ^ pushing back (www.theguardian.com)
  2. ^ new plan (aemo.com.au)
  3. ^ committed to (alp.org.au)
  4. ^ backed the plan (mobile.twitter.com)
  5. ^ We calculated emissions due to electricity loss on the power grid – globally, it's a lot (theconversation.com)
  6. ^ CC BY (creativecommons.org)
  7. ^ Yackandandah (totallyrenewableyack.org.au)
  8. ^ virtual transmission capacity (www.energy-storage.news)
  9. ^ Will NIMBYs sink new clean energy projects? The evidence says no – if developers listen to local concerns (theconversation.com)
  10. ^ Kennedy Energy Park (www.seetao.com)
  11. ^ regulations (obpr.pmc.gov.au)
  12. ^ Star of the South (reneweconomy.com.au)
  13. ^ 83% of us (www.ipsos.com)
  14. ^ often perceive (www.abc.net.au)
  15. ^ A 21st-century reinvention of the electric grid is crucial for solving the climate change crisis (theconversation.com)

Read more https://theconversation.com/a-clean-energy-grid-means-10-000km-of-new-transmission-lines-they-can-only-be-built-with-community-backing-187438

Times Magazine

Why Social Media Marketing Matters for Businesses in Australia

Today social media is a big part of daily life. All over Australia people use Facebook, Instagram, TikTok , LinkedIn and Twitter to stay connected, share updates and find new ideas. For businesses this means a great chance to reach new customers and...

Building an AI-First Culture in Your Company

AI isn't just something to think about anymore - it's becoming part of how we live and work, whether we like it or not. At the office, it definitely helps us move faster. But here's the thing: just using tools like ChatGPT or plugging AI into your wo...

Data Management Isn't Just About Tech—Here’s Why It’s a Human Problem Too

Photo by Kevin Kuby Manuel O. Diaz Jr.We live in a world drowning in data. Every click, swipe, medical scan, and financial transaction generates information, so much that managing it all has become one of the biggest challenges of our digital age. Bu...

Headless CMS in Digital Twins and 3D Product Experiences

Image by freepik As the metaverse becomes more advanced and accessible, it's clear that multiple sectors will use digital twins and 3D product experiences to visualize, connect, and streamline efforts better. A digital twin is a virtual replica of ...

The Decline of Hyper-Casual: How Mid-Core Mobile Games Took Over in 2025

In recent years, the mobile gaming landscape has undergone a significant transformation, with mid-core mobile games emerging as the dominant force in app stores by 2025. This shift is underpinned by changing user habits and evolving monetization tr...

Understanding ITIL 4 and PRINCE2 Project Management Synergy

Key Highlights ITIL 4 focuses on IT service management, emphasising continual improvement and value creation through modern digital transformation approaches. PRINCE2 project management supports systematic planning and execution of projects wit...

The Times Features

Jetstar announces first ever Brisbane to Rarotonga flights with launch fares from just $249^ one-way

Jetstar will start operating direct flights between Brisbane and Rarotonga, the stunning capital island of the Cook Islands, in May 2026, with launch sale fares available today...

Introducing the SE 2 and Mini hair dryers from Laifen

The Mane Attractions for Professional Styling at Home Without the Price Tag Fast, flawless hair is now possible with the launch of Laifen’s two professional quality hair dryers th...

Home Gym Recovery Routines: What Pro Athletes Do After Workouts

Training is only half the equation. What you do after your workout has just as much impact on your progress, performance, and long-term health. Professional athletes know this, w...

Flipping vs. Holding: Which Investment Strategy Is Right for You?

Are you wondering whether flipping a property or holding onto it is the better investment strategy? The answer isn’t one-size-fits-all. Both strategies have distinct advantages a...

Why Everyone's Talking About Sea Moss - And Should You Try It Too?

Sea moss - a humble marine plant that’s been used for centuries - is making a major comeback in modern wellness circles. And it’s not just a trend. With growing interest from athle...

A Guide to Smarter Real Estate Accounting: What You Might Be Overlooking

Real estate accounting can be a complex terrain, even for experienced investors and property managers. From tracking rental income to managing property expenses, the financial in...